top of page



Architecture by Cedar Company policy
BACKGROUND Architecture by Cedar was established on 12th June 2012 with the aim to provide architectural and construction related...


AAK Architect Magazine feature
One of our recently completed projects (the composed cuboid) was featured in the AAK's (Architectural Association of Kenya) magazine...


Kijani Ridge villa
We were engaged for design and construction supervision of a contemporary 4 bedroom villa in Kijani Ridge, Tatu city within Kiambu County, Kenya. The project is currently under construction. Here's a sequence of site activities for your better understanding of a typical construction process: Setting out - This normally comes after the contractor has taken possession of the site and completed his preliminaries/mobilization (site hoarding, toilet, safety installations, accesses
bottom of page